Why Does Route WW Need Improvements?
Bridges over Maupin and Ditch Creeks are both structurally and functionally obsolete. They are currently striped for one lane due to loading restrictions.
What Improvements on Route WW Will Be Accomplished?
MoDOT will replace both bridges at their current location. Approximately $1.5 million is budgeted for construction of this project.
How Will Traffic Be Impacted While Construction Is Under Way?
Detour Map
for Route WW
Road closure will be necessary during construction. One bridge will be closed at a time.
Maupin Creek Bridge will be constructed first and opened to traffic before closing and constructing Ditch Creek Bridge.
When Will Construction Take Place?
Construction begins in early March 2010. The project is expected to be complete in mid-September 2010.
Who Do I Contact For More Information?