Why is MoDOT doing this project?
Route 45 is a critical east/west route and capacity is expected to increase substantially by the year 2030. These improvements will accommodate economic development, and most important, improve traffic safety. It will also create a safe, efficient, environmentally sound, and economical transportation facility that meets the needs of the area.
How does this project benefit me?
Based on the current design, there are more than 80 access points available for vehicles to pull off the roadway. With the construction of an additional lane in each direction, vehicles will be able to go around stalled vehicles with no chance for a head on collision with opposing traffic. The design for the new roadway is also safer than the existing road.
What is the project time line?
Construction will be conducted in phases:
- Phase 1 (May thru Fall, 2010) — Temporary pavement construction on westbound lane of Route 45. This work includes grading, temporary asphalt pavement, culvert extensions, demolition work, temporary signals, etc.
- Phase 2 (Fall 2010 to Summer 2011) — Construct new eastbound lanes of Route 45. The work includes grading, concrete pavement , storm drainage, curb & gutter, lighting, share use path, etc.
- Phase 3 (Summer 2011 thru Summer 2012) — Includes construction of the new westbound lanes of Route 45. The work includes grading, concrete pavement , storm drainage, curb & gutter, MSE Walls, median, etc.
Contractors will strive to maintain one open lane of traffic in each direction at all times along Route 45 during construction. However, some side roads may need to be closed temporarily to rebuild them. Detoured routes will be in place during any such closes
How much does this project cost?
In November 2004, Missouri voters passed Amendment 3, which allowed the funding of new major projects including Route 45 between Route 9 and Route K.
How do I learn more?
For more information, review the project maps and materials listed in the left column. You can also submit a comment, send an e-mail or give us a call. Lend your voice to the transportation process! |

In July, crews were relocating utilities
to prepare for construction.

|